Christchurch · The roadworks comparison · 13 November 2026
Years of cones.
Still waiting for the payoff.
A pipe job ends, another starts, and the next improvement is still a year away. I’ve compared our patch of Mairehau, Burwood and Greenhaven with other Christchurch work. The long wait looks even harder to swallow when you put the scale of the work—and what we can actually use—alongside it.

As of 13 November, Mairehau Road is closed through the intersection in both directions. Burwood Road is getting through on one lane, taking turns under temporary traffic lights. That’s the situation on the ground here—not a normal, functioning roundabout.
The latest Council timetable now puts the extra pipe repairs into mid-November, followed by the remaining wastewater work, due to finish around 17 December. The last timetable had early November and early December. The dates have moved again. [1]
Our journeys don’t restart with each contract
It makes no sense to measure this only from the day the current excavation started. We’ve already had the Mairehau changes for new housing and the Prestons Park connection, the fresh-water work on Burwood, disruption around QEII, and Greenhaven being affected and used as a diversion. It all lands on the same neighbourhood.
- Mairehau and Prestons Park, 2023–24: the October 2023 developer update already had roadworks under way, including utilities and a new intersection. An April 2024 finish became September. By November 2024, the developer said its part was complete, with the second entrance still tied to subdivision titles. This delivered services and access for housing, but also left us living through a long stretch of changing road conditions. [2]
- Burwood, Stanford, Newhaven and Greenhaven: the water-main contract awarded in August 2024 covered Burwood in both directions from Mairehau, plus Stanford and Newhaven between Burwood and Greenhaven. Greenhaven itself was also affected and used as a diversion. The contract award gives the project’s place in the sequence; it isn’t the date every street closed. [3]
- Burwood by QEII: I also remember the fresh-water work on the approaches on both sides of QEII, with traffic down to one lane each way. My recollection is around August. That timing is approximate, so I haven’t turned it into another supposedly exact number of closure days.
- The current Mairehau diversion: Metro’s notice began on 9 June. By 13 November, that’s 157 days since the notice started, and the junction is still restricted. The restrictions have changed along the way; this isn’t 157 days of every approach being completely shut. [4]
- The intersection rebuild: the Community Board’s October report puts the start in late 2027. A start date. There’s still the construction period after that. [5]
That puts the documented sequence across more than three years already, with another major stage ahead. These aren’t three years of uninterrupted closure. They are years in which the same residents, shops and hospital journeys keep coming back into the work zone.
Put the time next to the size of the job
A long programme can be reasonable when it delivers a much bigger job. The useful comparison is the scope, the disruption and the improvements available at the end—not just the number of cones.
| Road / programme | Time and access | Size and functionality | What remains |
|---|---|---|---|
| Burwood–Mairehau and adjoining routes | Housing-related work documented by October 2023; later water and wastewater stages. Current detour notice spans 157 days so far. Mairehau through-movements remain closed; Burwood alternates on one lane. | Developer services and access; water-main renewals on four named corridors; local wastewater renewal. A future rebuilt intersection with signals and crossings. [2][3] | Wastewater target around 17 December 2026. Signals scheduled to start late 2027; finishing date still to come. [1][5] |
| Harewood / Gardiners / Breens, plus related Harewood pipe work | Signals/crossing package began November 2025 and was reported complete by April 2026—roughly five months between those updates. Further Harewood water-main work ran May–November 2026, maintaining two-way traffic. [6][9] | A signalised junction, a school signal crossing, other pedestrian improvements, about 500 metres of stormwater pipe and water-supply renewals in the initial package. [7] | The wider road has had more work; the new signals and school crossing are already delivered. Counting the related 2026 pipe stage gives a corridor sequence of about a year, rather than pretending everything took one week. |
| Lincoln Road, Wrights–Curletts and adjoining streets | Main programme: 8 June 2026 to mid-2027, roughly a year planned. Traffic management and side-road restrictions during construction. [11] | Wastewater and water upgrades, road rebuilding/widening, peak-hour bus lanes, shelters, lighting, fibre and underground power. A broader transport-and-services package. [10] | Under construction. A further road design and shared walking/cycling bridge approved on 4 November may finish alongside or after the main work, subject to land purchase. Mid-2027 isn’t a guaranteed end to every related stage. [10] |
| Wairakei / Aorangi / Nor’West Arc | Related cycleway, street and pipe work began January 2025, with that programme running to end-2027. A separate Wairakei trunk/collector upgrade runs August 2026–mid-2028. The combined calendar span is about 3½ years planned. [12][13] | Multiple streets, a larger wastewater trunk main and collector, water/stormwater work, street renewal and separated cycling connections. Stage-by-stage restrictions, including one-way traffic. | Substantial work remains. This is another neighbourhood facing a long sequence—but with a much broader network and street-building scope than one junction alone. |
The comparisons don’t make Burwood–Mairehau the longest programme in Christchurch. Wairakei is a reminder that big underground jobs really can take years. They do show that our repeated disruption has stretched well beyond the time taken to deliver a working signalised junction and crossings at Harewood, while our own junction improvement hasn’t even started.
Harewood shows what a useful milestone looks like
Harewood is the closest example of pipes and a junction improvement being tackled together. Its initial package combined traffic signals, crossings, stormwater and fresh-water work. Council described a coordinated approach, with intensive January work intended to shorten the disruption. [7]
That wasn’t a miracle seven-day project. Metro’s wider bus detours were extended to 25 January, and other work carried on. The project page reported the signals and school-crossing sections complete in April. [8][6]
Then Harewood had further water-main work later in 2026. It would be unfair to leave that out while counting every related job on our roads. Even so, Harewood residents had their new signals and school crossing in use while the wider programme continued. That’s a meaningful improvement delivered along the way.
Here, the long sequence has mostly given us renewed services, access for housing and repeated changes to how we get around. Those pipes matter. But the extra everyday transport functionality is modest compared with the broader packages elsewhere, and the promised safer junction is still ahead of us. The burden has arrived well before the full benefit.
And we’re nowhere near the end of the story
The December wastewater target won’t finish the intersection project. Late 2027 won’t either: that’s when the next construction stage is due to begin. From work already under way in October 2023 to a junction rebuild starting late in 2027 is roughly four years of calendar span, before allowing for that rebuild itself.
I’m not dismissing the work below the road. Reliable water and sewerage are essential, and the Prestons work did provide new services and access. But renewing pipes doesn’t automatically give us an easier school run, a safer crossing or a more convenient way to reach the shops. Those are the things we’re still waiting to see finished.
My view is that this is taking far too long for the relatively limited improvement to everyday travel delivered so far. Harewood shows a similar kind of junction benefit arriving much sooner; Lincoln shows a much larger bundle being tackled in roughly a year, even with more work beyond it. We’re bearing the cumulative cost of separate stages without a clear finish for the whole neighbourhood.
The fair demand is a joined-up programme for Mairehau, Burwood, Greenhaven and the diversion routes, with usable improvements delivered as it goes. A contractor finishing one section shouldn’t wipe the slate clean on everything residents have already put up with—or on the work still to come.
This is a comparison of project scope, calendar span and access—not an engineering productivity score. Pipe depths, ground conditions, lengths and construction methods differ. A five-month detour and a five-month construction programme aren’t identical measures. Overlaps count once, future dates remain targets, and local recollections are marked as such.
Links and sources
Public project information and local observations as at 13 November 2026. The current closure, Greenhaven’s diversion role and the QEII approach disruption are my local account; the QEII date is approximate.
- Council: Burwood wastewater upgrade
Current programme: extra repairs to mid-November; remaining work expected around 17 December 2026.
- Prestons Park developer updates
October 2023 update: work under way and April 2024 target. August 2024 update: September target. November 2024 update: developer portion complete, second access linked to titles.
- GETS: Water Supply Mains Burwood, Stanford & Newhaven Renewals
RFx 28207552: four named corridors; awarded 14 August 2024. Contract scope, not a complete closure diary.
- Metro: Route 7
Mairehau westbound diversion from 9 June 2026, still listed on 13 November. Elapsed days calculated by subtracting those dates.
- Community Board agenda, 5 October 2026
Item 18, section 3.2: Burwood/Mairehau construction scheduled to start late 2027.
- Council: Wheels to Wings staged approach
November 2025 start; April 2026 update reports the Harewood junction and school-crossing sections complete. Other route sections remain.
- Council: Safety and water upgrades on Harewood Road, 11 November 2025
Initial signals, crossings, water renewals and approximately 500 metres of stormwater work; coordinated delivery and planned intensive January work.
- Metro: Harewood Road Super Week detours
Wider bus detours extended to 25 January 2026. The seven-day intensive phase was not the whole project.
- Council: Northwest water and roading upgrades
Related Harewood water-main programme, May–November 2026, with two-way traffic maintained. Also lists Wairakei and surrounding project stages.
- Council: Lincoln Road water and roading upgrades
Main scope and mid-2027 target. The 4 November update adds the Annex–Curletts design and bridge, subject to land purchase and potentially finishing later.
- Isaac Construction: Lincoln Road FAQs
8 June 2026 start, mid-2027 target and access arrangements.
- Council: Nor’West Arc cycleway and wastewater upgrades
January 2025–end-2027 programme; multiple streets, utilities, cycling and street-renewal work.
- Council: Wairakei pipe upgrades, 18 August 2026
Large-diameter trunk and collector mains, deep trenching and dewatering, starting 24 August 2026, with mid-2028 completion expected.